High-runner extrusion film lines lost 12+ hours per die changeover due to disorganized tool preparation and unstandardized procedures.
Client Situation & Operational Bottlenecks:
- •Extrusion die setup downtime averaging 12 hours per product run
- •Unorganized tool locating and missing specialized wrenches during changeovers
- •Frequent micro-stoppages and polymer trim scrap during line restarts
- •Overall Equipment Effectiveness (OEE) trapped at a low 42%
Our Approach
- Conducted video SMED (Single-Minute Exchange of Die) audit of changeover steps
- Categorized changeover tasks into internal (machine stopped) and external (machine running) elements
- Converted internal die pre-heating tasks into external prep activities
- Designed standardized color-coded tooling carts and quick-clamping fixtures
- Established visual OEE tracking boards and Autonomous Maintenance routines
Key Improvement Initiatives
- 1Rolled out standardized SMED changeover checklists and timing sheets
- 2Installed pre-heating stations for extrusion die tools next to production lines
- 3Trained machine operators and maintenance crews on parallel changeover execution
- 4Instituted 6 Big Losses downtime tracking and 5-Why root cause analysis
Before vs. After Operational Metrics
| Metric | Before Transformation | After Transformation | Quantified Impact |
|---|---|---|---|
| Extrusion Line Changeover | 12 hours | 7.4 hours | -38% |
| Overall Equipment Effectiveness (OEE) | 42% | 60% | +18% |
| Unplanned Breakdown Hours | 85 hrs/mo | 32 hrs/mo | -62% |
“
Reducing our die changeover time from 12 hours down to 7.4 hours gave us immense flexibility. Our OEE jumped 18% in just 90 days.
— VP Operations, Flexible Packaging & Extrusion Plant
KEY RESULTS
38%Changeover Time Cut
18%OEE Uplift Achieved
62%Breakdown Downtime Cut
Services Delivered
- OEE Improvement
- SMED Quick Changeover
- Total Productive Maintenance
- 5S & Visual Management
- Process Excellence
Methodologies Used
SMEDTPMOEE Improvement5SKaizen6 Big Losses
Service Capability
OEE Improvement
Maximize equipment availability, performance rate, and quality output on critical assets.
Ready to Achieve Similar Improvements?
Speak with our manufacturing consultants to discuss similar operational improvement opportunities for your plant.
Request a Manufacturing Assessment